RANGE OF CONTEMPLATED REMEDIATON ALTERNATIVES
Clean up or Cover up?
Following
are excerpts from the Department of Ecology's Draft
Supplemental Feasibility Study for the Whatcom Waterway site (1.2mb
PDF).
That document was prepared by G-P's consultants to describe to
the State what measures are implied by which standards, and what actions
are appropriate according to which goals. Therefore a range of options
has been proposed. This comes from a consensus-based, agency-driven
process - a process characterized by conflict aversion and the stark
absence of citizen or victim representation.
These "Alternatives" detail options from removing all
to none of the contaminated sediment in the Whatcom
Waterway project area. Despite years of participation in the Bay
Action Group, the Port's proposals for the G-P acquisition project are
a sudden departure from the framework developed to date. The Port's
proposal removes the least amount of polluted sediment from the bay,
leaving most in place, some capped and left to follow the "Natural
Recovery" approach championed by G-P's Chip Hilardes. G-P's
treatment lagoon, recently contemplated as contaminated sediment repository,
is instead converted to a yacht basin. Uplands would be remediated according
to remedial investigations underway and eventually sold off to the private
sector.
These
documents are worth reading because they underscore several important
:features of the Bellingham Bay situation, namely:
1) No agency has ever made any effort whatsoever to make G-P clean
up their mercury mess for almost forty years since it started, thirty
seven years since it was generally known to be harmful and twenty-some
years since they claim to have "controlled" their discharges
of mercury.
2) Every agency effort has been to spare costs to Georgia-Pacific,
including the enablement of two different storage repository schemes
on state aquatic lands, including the re-designation of former aquatic
lands as "upland" - and no alternative that involves shipping
wastes to existing approved landfills.
3) G-P has exploited regulatory inaction to carefully measure a long-term
rate of "natural recovery",
subsequently parlaying that data into a rationale for continued inaction
- even oddly converting the hottest mercury hotspots, like the logpond,
into "estuaries" or "habitat areas" with the simple
expedient of dumping a little dirt on top of them.
The
foregoing points will shed a somewhat different light on the alternatives
than was originally intended.
The
alternatives' summary follows: WW means Whatcom Waterway, SQS means
sediment quality standards, CDF means confined disposal facility, etc.
Look to see how many cubic yards are actually being removed, and where
they are being put, how much is being covered up? Look also at some
typical project costs.
" Remedial Alternative A: No Action (Pilot No. 1). Under
this alternative, there would be no sediment cleanup, habitat restoration,
monitoring activities, or land use actions. The exiting Log Pond cap
would be maintained, and the existing Bay sediments would continue to
recover naturally over time.
" Remedial Alternative B: Source Control & Natural Recovery
with Capping. All action alternatives evaluated in the RI/FS and this
Supplemental FS (i.e., Identification and Assembly of Cleanup Technologies
Supplemental Feasibility Study 15 March 2002 Whatcom Waterway Site,
Bellingham, Washington 000030-07 T6 Alternatives B through J) include
source controls. This alternative would utilize natural recovery in
those parts of the WW Area that are predicted to naturally achieve SQS
criteria within approximately 3 years (by 2005), which is as rapid as
biological resources could potentially recover at the site following
a more active cleanup (e.g., dredging). Those areas of the site that
are not predicted to recover, and which occur outside of the navigation
channel, would be capped with a 1- to 3- foot sand layer. A relatively
small area in the middle of the Whatcom Waterway that is predicted to
recover by 2005, partly as a result of resuspension-related transport,
would be left to recover naturally. Other site units within the WW Area
that currently exceed the mercury bioaccumulation screening level (BSL;
1.2 mg/kg) would be capped to accelerate the natural recovery process.
The existing sediment remediation/habitat restoration cap placed in
the Log Pond as an interim action would be maintained. All cleanup areas
of the site would be monitored to document sediment recovery using a
combination of chemical and biological testing methods. No dredging
would occur under this alternative. A layout of Alternative B is presented
in Figure
4.
" Remedial Alternative C: Capping & Removal to Improve
Navigation (Log Pond Nearshore CDF). This alternative combines capping
and limited dredging within the middle of the Whatcom Waterway navigation
channel to achieve SQS criteria throughout the WW Area. As in Alternative
B, those areas of the site that are not predicted to recover (using
conservative modeling assumptions), and which occur outside of the navigation
channel, would be capped with a 1- to 3-foot sand layer. No further
action would be undertaken in the outer Whatcom Waterway reach where
surface sediments currently meet SQS criteria and where channel depths
are consistent with the federally authorized elevations. Surface and
subsurface sediments within the middle of the Whatcom Waterway adjacent
to the G-P Log Pond would be dredged to a depth of at least 5 feet below
the currently authorized channel depths. Since subsurface contaminants
would still be present below the dredge depth, the dredge cut would
be capped with a 2-to-3- foot clean sand layer, resulting in a final
channel elevation at least 2 feet below the authorized depth. This dredge-and-cap
action would leave sufficient tolerance to Identification and Assembly
of Cleanup Technologies Supplemental Feasibility Study 16 March 2002
Whatcom Waterway Site, Bellingham, Washington 000030-07 T6 allow unencumbered
future maintenance dredging of the authorized federal channel in this
area, considering typical overdredge allowances. No action would be
undertaken at the head of the Whatcom Waterway (i.e., above Station
15+00), as this area (currently exceeding SQS but below MCUL biological
criteria) would be left to recover naturally to below the SQS by 2005.
An estimated 160,000 CY of sediments would be dredged under this alternative.
Dredged sediments could be reused to create a nearshore CDF in the G-P
Log Pond. Excess sediments that do not fit into the nearshore fill would
be disposed at an offsite upland landfill. Habitat mitigation actions
including at least 6 acres of area-forarea replacement by fill removal
and/or acquisition and enhancement at high priority habitat creation
sites would be performed as a part of implementation of this alternative.
A layout of Alternative C is presented in Figure
5.
" Remedial Alternative D: Capping & Removal to Improve
Navigation (Upland Disposal). This alternative is identical to Alternative
C except that all of the dredged material would be disposed at an upland
landfill instead of in the G-P Log Pond nearshore CDF. The dredge material
would either be reused to restore a wetland habitat at the Whatcom-Skagit
Phyllite Quarry, or, alternatively, disposed at the Roosevelt Regional
landfill. The existing sediment remediation/habitat restoration cap
placed in the Log Pond as an interim action would be maintained. A layout
of Alternative D is presented in Figure
6.
" Remedial Alternative E: Capping & Removal to Achieve
Authorized Channel Depths (CAD Disposal) (Pilot No. 2A). The overall
objective of this alternative is to achieve SQS criteria in the WW Area
while concurrently maintaining existing navigation channels, minimizing
dredging and disposal of contaminated sediment, and maximizing the areal
extent and diversity of intertidal aquatic habitat by using caps and
CAD facilities. Enough material would be dredged from the Whatcom Waterway
to remove contaminated sediments from the existing federal channel (including
overdredge allowances) in all areas of the waterway that are currently
used for navigation. Except for the extreme head of the Whatcom Waterway
that currently contains mudflat habitat, surface and subsurface sediments
throughout Identification and Assembly of Cleanup Technologies Supplemental
Feasibility Study 17 March 2002 Whatcom Waterway Site, Bellingham, Washington
000030-07 T6 much of the waterway would be dredged to a depth of at
least 5 feet below the currently authorized channel depths. However,
no further action would be undertaken in the outer Whatcom Waterway
reach where surface sediments currently meet state standards and where
channel depths are consistent with the federally authorized elevations.
Other contaminated sediment areas would be capped with a 1-to-3-foot
clean sand layer. In this alternative a 3-acre area of mudflat and adjacent
shallow subtidal habitat would be left intact at the head of the Whatcom
Waterway. The existing sediment remediation/habitat restoration cap
placed in the Log Pond as an interim action would be maintained. Approximately
360,000 CY of contaminated sediment from navigation areas within the
Whatcom Waterway would be dredged. In this alternative, the sediment
disposal capacity would be provided by a 400,000 to 500,000 CY CAD sited
in the Starr Rock/Cornwall area. The Starr Rock/Cornwall CAD could also
be implemented as a multi-user disposal facility to contain contaminated
sediments that may be dredged from other sites in Bellingham Bay. The
CAD would provide opportunities for concurrent habitat restoration.
Largely because of the CAD, approximately 42 acres of subtidal area
would be converted into intertidal habitat. A layout of Alternative
E is presented in Figure
7.
" Remedial Alternative F: Capping & Removal to Achieve
Authorized Channel Depths (Upland Disposal) (Pilot No. 2B). The overall
objective of Alternative F is to achieve SQS criteria in the WW Area
while maintaining existing navigation channels and minimizing dredging
and disposal of contaminated sediment. This alternative includes the
same amount of dredging as Alternative E, but would dispose of the materials
at one or more off-site upland landfills. Other contaminated sediment
areas would be capped with a 1-to-3-foot clean sand layer. The existing
sediment remediation/habitat restoration cap placed in the Log Pond
as an interim action would be maintained. All dredged sediments would
be offloaded on shore, dewatered as necessary to facilitate transport,
and hauled by rail, truck, and/or barge outside of the Bellingham Bay
watershed to upland disposal facilities. Approximately 360,000 CY of
Identification and Assembly of Cleanup Technologies Supplemental Feasibility
Study 18 March 2002 Whatcom Waterway Site, Bellingham, Washington 000030-07
T6 contaminated sediment from navigation areas within the Whatcom Waterway
would be dredged. In this alternative, the Whatcom-Skagit Phyllite Quarry
or the Roosevelt Regional Landfill would provide the sediment disposal
capacity. A layout of Alternative F is presented in Figure
8.
" Remedial Alternative G: Full Removal from Navigation
Areas (CAD Disposal) (Pilot No. 2C). The overall objective of this alternative
is to achieve SQS criteria in the WW Area, allowing for possible future
deepening of the navigation channels, and maximizing the areal extent
and diversity of intertidal aquatic habitat by using caps and CAD facilities.
Unlike Alternative E, minimizing dredging and disposal volumes is not
a primary objective of Alternative G. Contaminated sediments that are
located within the Whatcom Waterway, even if present below the currently
authorized depths, would be dredged, removing potential encumbrances
to channel deepening, should such a deepening project be undertaken
in the future. Dredging would be performed throughout the Whatcom Waterway,
including a 1-acre area at the head of the waterway. The extreme head
of the Whatcom Waterway near the former Citizens Dock, consisting of
a 2-acre area of mudflats that has formed naturally within this area,
would be left intact. The existing sediment remediation/habitat restoration
cap placed in the Log Pond as an interim action would be maintained.
Approximately 760,000 CY of contaminated sediment from navigation areas
within and adjacent to the Whatcom Waterway would be dredged. In this
alternative, the sediment disposal capacity would be provided by a 800,000
to 1,000,000 CY CAD sited in the Starr Rock/Cornwall area. The Starr
Rock/Cornwall CAD could also be implemented as a multi-user disposal
facility to contain contaminated sediments that may be dredged from
other sites in Bellingham Bay. The CAD would provide concurrent habitat
restoration. Largely because of the CADs, approximately 63 acres of
subtidal area would be converted into intertidal area. A layout of Alternative
G is presented in Figure
9.
" Remedial Alternative H: Full Removal from Navigation
Areas and Partial Removal from the G-P ASB and Starr Rock Areas (Upland
Disposal) (Pilot No. Identification and Assembly of Cleanup Technologies
Supplemental Feasibility Study 19 March 2002 Whatcom Waterway Site,
Bellingham, Washington 000030-07 T6 2D). Similar in some respects to
Alternative G, the overall objective of Alternative H is to achieve
SQS criteria in the WW Area, allowing for potential future deepening
of the navigation channels. This alternative includes dredging of those
areas included in Alternative G, but also includes the dredging of an
additional 300,000 CY of sediments exceeding the site-specific BSL criteria
that are located offshore of the G-P ASB and at the former Starr Rock
disposal site. The dredged sediments would be disposed at one or more
off-site upland landfills. Other contaminated sediment areas would be
capped with a 1-to-3-foot clean sand layer. The existing sediment remediation/habitat
restoration cap placed in the Log Pond as an interim action would be
maintained. All dredged sediments would be offloaded on shore, dewatered
as necessary to facilitate transport, and hauled by rail, truck, and/or
barge outside of the Bellingham Bay watershed to upland disposal facilities.
Approximately 1,100,000 CY of contaminated sediment from the WW Area
would be dredged. In this alternative, the sediment disposal capacity
would occur at the same upland disposal facilities described for Alternative
F. A layout of Alternative H is presented in Figure
10.
" Remedial Alternative I: Full Removal from Public Lands
(Upland Disposal) (Pilot No. 2E). The overall objective of Alternative
I is to completely remove all contaminated sediment from public lands
within the WW Area, and totally avoid disposal in the aquatic environment.
The existing sediment remediation/habitat restoration cap placed in
the Log Pond as an interim action would be maintained. This alternative
would also allow for possible future deepening of the navigation channels
and state-owned harbor areas. Like Alternative H, avoiding disposal
in the aquatic environment is a primary objective. With the exception
of sediments located immediately adjacent to the existing G-P wastewater
pipeline and at the Log Pond, dredging would be performed within all
reaches of the WW Area, including the extreme head of the federal channel,
encompassing the former Citizens Dock and associated mudflat areas.
All dredged sediments would be offloaded on shore, dewatered as necessary
to facilitate transport, and hauled by rail and/or truck outside of
the Bellingham Bay watershed to upland disposal facilities. Approximately
1,900,000 CY of contaminated sediment from the WW Area would be Identification
and Assembly of Cleanup Technologies Supplemental Feasibility Study
20 March 2002 Whatcom Waterway Site, Bellingham, Washington 000030-07
T6 dredged. In this alternative, the sediment disposal capacity would
be provided by the same upland disposal facilities described for Alternative
F. A layout of Alternative I is presented in Figure
11.
" Remedial
Alternative J: Full Removal from Navigation Areas (G-P ASB Upland
Disposal) (Supplemental EIS Modified Preferred Near-Term Remedial Action
Alternative). Similar in some respects to Alternative G, the overall
objective of Alternative J is to achieve SQS criteria in the WW Area,
allowing for potential future deepening of the navigation channels,
but avoiding disposal in the aquatic environment. Sediments in the navigation
areas would be removed using hydraulic cutterhead dredges, and material
would be disposed at the G-P ASB upland CDF. Existing habitat at the
head of Whatcom Waterway would be protected, while accommodating public
access improvements as proposed by the City of Bellingham. The existing
sediment remediation/habitat restoration cap placed in the Log Pond
as an interim action would be maintained. Whatcom Waterway would be
dredged, including the maximum practicable removal of contaminated sediments
from the federal channel, providing for future navigation flexibility.
Steep slopes at Starr Rock would also be dredged. Where technically
feasible, all contaminated sediments in the mid and outer Whatcom Waterway
Federal Channel would be removed. The exception would be a relatively
small volume of materials immediately adjacent to the G-P wastewater
pipeline. Depending on final design, the total dredge volume from the
Whatcom Waterway may approach approximately 760,000 CY. Prospective
dredging areas located in the outer Whatcom Waterway navigation channel
(e.g., units 1A and 1B; approximately 170,000 CY) would be evaluated
during remedial design to determine whether sediments in these areas
may meet regulatory criteria for unconfined, open-water disposal. Sediments
meeting appropriate criteria may be beneficially reused either within
the inner Bay for fills to enhance habitat function, or as ASB cap materials.
Dredged material that does not meet these criteria would require confined
disposal in the ASB."